Substation Scout

Black Oak - Hatfield substation interconnection queue

3 active projects totaling 1,491.1 MW in the PJM queue.

Target commercial operation dates as filed run from Mar 2029 to May 2031 (3 filings). 3 active filings target a date after November 27, 2026.

Transmission owner as filed: APS (3 filings).

3active projects
1,491.1active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1958 Black Oak - Hatfield 500 kV 500 931.1 Gas Active May 2031
C01-1333 Black Oak - Hatfield 500 kV 500 500 Battery Active Dec 2030
C01-1617 Black Oak - Hatfield 500 kV 500 60 Battery Active Mar 2029

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Fayette County, PA

All 56 PJM queue filings in Fayette County, PA.

Other PJM queue substations in Garrett County, MD

All 32 PJM queue filings in Garrett County, MD.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first