Black Oak - Hatfield substation interconnection queue
3 active projects totalling 1,491.1 MW in the PJM queue.
3active projects
1,491.1active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1958 | Black Oak - Hatfield 500 kV | 500 | 931.1 | Gas | Active |
| C01-1333 | Black Oak - Hatfield 500 kV | 500 | 500 | Battery | Active |
| C01-1617 | Black Oak - Hatfield 500 kV | 500 | 60 | Battery | Active |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.