Roth Rock substation interconnection queue
1 active project totaling 43.5 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Roth Rock as the point of interconnection, all in Garrett County, MD.
Target commercial operation dates as filed run from Dec 2008 to Jun 2030 (2 filings). 1 active filing targets a date after November 27, 2026.
Transmission owner as filed: APS (1 filing).
1active projects
43.5active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| C01-1547 | Roth Rock 138 kV | 138 | 43.5 | Battery | Active | Jun 2030 |
| N29 | Roth Rock 138kV | 138 | 8 | Wind | Withdrawn | Dec 2008 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Garrett County, MD
- Black Oak - Hatfield: 3 active, 1,491.1 MW of 3 filed
- Mount Storm - Pruntytown: 2 active, 231 MW of 2 filed
- Kelso Gap: 3 active, 126 MW of 3 filed
- Albright-Cross School: none active of 2 filed
- Oakland-Gorman: none active of 2 filed