Home / PJM / substation / Hatfield - Rhodes Lane
Hatfield - Rhodes Lane substation interconnection queue
3 active projects
totalling 4,038 MW in the PJM queue.
3 active projects
4,038 active MW
3 total filed
Queue ID Project kV MW Resource Status
C01-2105
Hatfield - Rhodes Lane 500 kV
500
1,400
Gas
Active
C01-2228
Hatfield - Rhodes Lane 500 kV
500
1,338
Gas
Active
C01-1763
Hatfield - Rhodes Lane 500 kV
500
1,300
Gas
Active
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with PJM before relying on these figures.
Site Scanner draws on HIFLD substations and electric retail service
territories, USGS watershed boundaries, FEMA flood hazard layers and US Census
geocoding. Queue data is compiled from public interconnection
queue filings. Every figure carries its source and retrieval date.
A withdrawal records that a request left the queue. It says
nothing about injection capacity at that location. Verify with the relevant ISO before
relying on any figure. Queue datasets are tracked separately and are
not directly comparable: status vocabularies, fuel coding, and publication
cadence all differ.
Screening aid only. Not a system impact study. Contiguous US.