South Union substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name South Union as the point of interconnection, all in Fayette County, PA.
Target commercial operation dates as filed run from Dec 2024 to Apr 2026 (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AI1-199 | South Union 25 kV | 25 | 7 | Hybrid | Withdrawn | Dec 2024 |
| AF2-292 | FA-Morgantown | 12.5 | 0 | Hybrid | Withdrawn | Apr 2026 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Fayette County, PA
- Hatfield - Rhodes Lane: 3 active, 4,038 MW of 3 filed
- Black Oak - Hatfield: 3 active, 1,491.1 MW of 3 filed
- Ronco: 2 active, 665 MW of 3 filed
- Gans - South Union: 1 active, 200 MW of 2 filed
- Lardin - Lake Lynn: 3 active, 119 MW of 3 filed
- Gans: 2 active, 98.1 MW of 4 filed
- Bethelboro: 1 active, 60 MW of 3 filed
- Mill Run: 2 active, 18 MW of 4 filed
- Gates Hill: none active of 2 filed
- Lardin: none active of 2 filed
- Yukon-Bethelboro: none active of 2 filed
Site Scanner