Ronco substation interconnection queue

2 active projects totaling 665 MW in the PJM queue, plus 1 with terminal status (shown grayed).

3 PJM queue filings name Ronco as the point of interconnection, all in Fayette County, PA.

Target commercial operation dates as filed run from Jun 2003 to Oct 2028 (3 filings).

2active projects
665active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
E17_W27 Ronco CT1, CT2, STG n/r 620 Gas In Service Jun 2003
AA2-139 Fayette Energy Facility 500 45 Gas In Service Oct 2017
AF2-029 Fayette Energy Facility 500 8 Battery Withdrawn Oct 2028

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Fayette County, PA

All 56 PJM queue filings in Fayette County, PA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first