Bergen substation interconnection queue
12 active projects totaling 1,192.4 MW in the PJM queue, plus 10 with terminal status (shown grayed).
Target commercial operation dates as filed run from Jun 2002 to Apr 2029 (22 filings). 3 active filings target a date after November 27, 2026.
Transmission owner as filed: PSEG (2 filings).
12active projects
1,192.4active MW
22total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| U2-100 | Bergen 230kV | 230 | 800 | Not reported | Withdrawn | Dec 2011 |
| Q75 | Bergen 230kV | 230 | 685 | Not reported | Withdrawn | Jun 2010 |
| AA1-039 | Bergen 230kV | 230 | 660 | Not reported | Withdrawn | Jun 2016 |
| A05 | Bergen | n/r | 500 | Gas | In Service | Jun 2002 |
| O66 | Hudson Transmission Project | 230 | 320 | Not reported | In Service | May 2013 |
| AF2-414 | Bergen 345 kV | 345 | 300 | Battery | Withdrawn | Jun 2023 |
| T159 | Bergen 230kV | 230 | 230 | Gas | Withdrawn | Jun 2011 |
| C01-1270 | Bergen 138 kV | 138 | 175 | Battery | Withdrawn | Apr 2029 |
| AF2-415 | Two Rivers Storage | 138 | 150 | Battery | Engineering and Procurement | Dec 2028 |
| AH1-703 | Bergen 230kV | 230 | 51.3 | Gas | Active | May 2027 |
| AB2-092 | Bergen Generating Station | 138 | 51.1 | Gas | Partially in Service - Under Construction | Jun 2027 |
| G10 | Bergen #2 | n/r | 50 | Gas | In Service | Jun 2002 |
| Y3-107 | Bergen 230kV | 230 | 45 | Gas | In Service | Apr 2015 |
| AH2-194 | Bergen 138kV | 138 | 20 | Gas | Withdrawn | Apr 2026 |
| AF2-416 | Railroad Avenue Energy Storage | 26 | 10 | Battery | Withdrawn | Jun 2025 |
| V4-019 | Bergen Generating Station | 230 | 10 | Gas | In Service | Jun 2013 |
| Y3-052 | Bergen | n/r | 10 | Gas | In Service | Mar 2015 |
| Y3-045 | Bergen Genertating Station | n/r | 5 | Gas | In Service | Mar 2015 |
| AD1-054 | Bergen 13kV | 13 | 0 | Solar | In Service | Oct 2019 |
| AG1-055 | Bergen 230 kV | 230 | 0 | Not reported | Withdrawn | Jun 2022 |
| AH1-008 | Bergen 230 kV | 230 | 0 | Not reported | Withdrawn | Dec 2026 |
| V1-034 | Hudson Transmission Project | 230 | 0 | Not reported | In Service | May 2013 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Tracked changes at this substation
1 change to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-10-05 | C01-1270 | Terminal status | 175 | Active → Withdrawn |
Other PJM queue substations in Bergen County, NJ
- Fairlawn: 1 active, 20 MW of 4 filed
- Marion: 3 active, 6.7 MW of 4 filed
- Kingsland: none active of 6 filed
- West Hempfield: none active of 3 filed
Other PJM queue substations in Hudson County, NJ
Other PJM queue substations in Union County, OH
- Marysville: 4 active, 280.8 MW of 9 filed
- Blue Jacket-Kirby: 1 active, 96.4 MW of 3 filed
- Eagle Road: none active of 3 filed
- Honda Marysville Tap: none active of 3 filed
- Mechanicsburg - Darby: none active of 3 filed
- Marysville-Tangy: none active of 2 filed