Substation Scout

Mason substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
AE1-055 Mason 230 kV 230 134 Hybrid Withdrawn
AF1-052 Mason 230 kV 230 114.2 Hybrid Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.