Substation Scout

Lynx substation interconnection queue

4 active projects totalling 363.4 MW in the ERCOT queue.

4active projects
363.4active MW
4total filed
Queue IDProjectkVMWResourceStatus
22INR0385 BRP Pictor BESS 138 201.1 Battery SS Completed, FIS Started, No IA
29INR0287 Valentine Energy Center 138 162.3 Gas SS Completed, FIS Started, No IA
18INR0079 Woodward I repower 138 0 Wind SS Completed, FIS Completed, IA
18INR0080 Woodward 2 repower 138 0 Wind SS Completed, FIS Completed, IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.