TNCENTRY2_1 substation interconnection queue

2 active projects totaling 303.6 MW in the ERCOT queue.

2 ERCOT queue filings name TNCENTRY2_1 as the point of interconnection, all in Pecos County, TX.

Target commercial operation dates as filed run from Mar 2028 to Dec 2028 (2 filings). 2 active filings target a date after November 27, 2026.

Interconnecting entity as filed: CENTURY GAS PROCESSING, LLC (2 filings).

2active projects
303.6active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
24INR0454 Longfellow Solar II 138 197.8 Solar SS Completed, FIS Started, IA Dec 2028
24INR0455 Longfellow BESS II 138 105.8 Battery SS Completed, FIS Completed, IA Mar 2028

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Tracked changes at this substation

1 change to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-11-0924INR0454Capacity revised−9.6 SS Completed, FIS Started, IA → SS Completed, FIS Started, IA

Other ERCOT queue substations in Pecos County, TX

All 63 ERCOT queue filings in Pecos County, TX.