Soda Lake (#) substation interconnection queue
4 active projects totalling 813.9 MW in the ERCOT queue.
4active projects
813.9active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 24INR0383 | Soda Lake BESS 2 SLF | 138 | 205.4 | Battery | SS Completed, FIS Started, No IA |
| 28INR0389 | Tri-X BESS 1 SLF | 138 | 205.3 | Battery | SS Completed, FIS Started, No IA |
| 23INR0080 | Soda Lake Solar 2 SLF | 138 | 201.7 | Solar | SS Completed, FIS Started, IA |
| 20INR0143 | Tri-X Solar 1 SLF | 138 | 201.5 | Solar | SS Completed, FIS Started, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.