Substation Scout

Lynx

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Pecos County. First named in the release with data as of June 1, 2016.

Pecoscounty as printed
138kV
AEP TNCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Pecos, TX: ERCOT queue, 58 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Fort Stockton Plant to Lynx: Rebuild 138 kV Line
Rehab the Fort Stockton Plant to Lynx 138 kV line
ERCOT project 86829 · RPG 23RPG008
AEP TNC
Tier 4
Planned
Future tab
138 May 2028 Fort Stockton Plant to Lynx
Pecos County
Fort Stockton Plant, Lynx

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202686829Projected in-service dateJan 2027 → May 2028
February 1, 202586829Projected in-service dateSep 2026 → Jan 2027
October 1, 202486829First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first