Tap Solstice to Bottlebrush substation interconnection queue
5 active projects totaling 1,513.2 MW in the ERCOT queue.
5 ERCOT queue filings name Tap Solstice to Bottlebrush as the point of interconnection, all in Pecos County, TX.
Target commercial operation dates as filed run from Mar 2029 to Oct 2029 (5 filings). 5 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Glass Mountain Solar, LLC (1 filing), Glass Mountain Solar II, LLC (1 filing), Glass Mountain Solar V, LLC (1 filing), Glass Mountain Solar III, LLC (1 filing), Glass Mountain Solar IV, LLC (1 filing).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 29INR0347 | Glass Mountain BB Solar 1 | 345 | 302.7 | Solar | SS Completed, FIS Started, No IA | Mar 2029 |
| 29INR0348 | Glass Mountain BB Solar 2 | 345 | 302.7 | Solar | SS Completed, FIS Started, No IA | Mar 2029 |
| 29INR0349 | Glass Mountain BB Solar 5 | 345 | 302.6 | Solar | SS Completed, FIS Started, No IA | Oct 2029 |
| 29INR0357 | Glass Mountain BB Solar 3 | 345 | 302.6 | Solar | SS Completed, FIS Started, No IA | Oct 2029 |
| 29INR0358 | Glass Mountain BB Solar 4 | 345 | 302.6 | Solar | SS Completed, FIS Started, No IA | Oct 2029 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Tracked changes at this substation
5 changes to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-09-07 | 29INR0347 | Status change | n/a | SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA |
| 2026-09-07 | 29INR0348 | Status change | n/a | SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA |
| 2026-09-07 | 29INR0349 | Status change | n/a | SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA |
| 2026-09-07 | 29INR0357 | Status change | n/a | SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA |
| 2026-09-07 | 29INR0358 | Status change | n/a | SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA |
Other ERCOT queue substations in Pecos County, TX
- Tap TNMP White Baker–Bottlebrush 345-kV double-circuit: 3 active, 3,009.2 MW of 3 filed
- Tap Solstice - Bakersfield Double circuit line: 3 active, 3,008.3 MW of 3 filed
- Tap SOLSTICE - SANDLAKE_5: 4 active, 1,633.7 MW of 4 filed
- TNCENTRY1_1: 3 active, 763.2 MW of 3 filed
- Tap Coyanosa - Blair Lake Sub: 2 active, 605.3 MW of 2 filed
- Tap # HOLIDAY SUB TNP - # SOAPTREE TNP: 2 active, 402.3 MW of 2 filed
- LEON_CRK: 2 active, 401.4 MW of 2 filed
- Lynx: 4 active, 363.4 MW of 4 filed
- 860 GIRVINSW: 3 active, 317 MW of 3 filed
- TNCENTRY2_1: 2 active, 303.6 MW of 2 filed