Substation Scout

Tap # HOLIDAY SUB TNP - # SOAPTREE TNP substation interconnection queue

2 active projects totalling 402.3 MW in the ERCOT queue.

2active projects
402.3active MW
2total filed
Queue IDProjectkVMWResourceStatus
27INR0438 Wisdom Solar SLF 138 299.4 Solar SS Completed, FIS Completed, No IA
27INR0440 Wisdom BESS SLF 138 102.9 Battery SS Completed, FIS Completed, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.