Tap Solstice - Bakersfield Double circuit line substation interconnection queue
3 active projects totaling 3,008.3 MW in the ERCOT queue.
3 ERCOT queue filings name Tap Solstice - Bakersfield Double circuit line as the point of interconnection, all in Pecos County, TX.
Target commercial operation date as filed: Jun 2030 (3 filings). 3 active filings target a date after November 27, 2026.
Interconnecting entity as filed: S&S Renewables, LLC (3 filings).
3active projects
3,008.3active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 30INR0084 | Gravitas I Natural Gas | 345 | 1,247 | Gas | SS Completed, FIS Started, No IA | Jun 2030 |
| 30INR0083 | Gravitas I Solar | 345 | 1,124.8 | Solar | SS Completed, FIS Started, No IA | Jun 2030 |
| 30INR0085 | Gravitas I Wind | 345 | 636.5 | Wind | SS Completed, FIS Started, No IA | Jun 2030 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Pecos County, TX
- Tap TNMP White Baker–Bottlebrush 345-kV double-circuit: 3 active, 3,009.2 MW of 3 filed
- Tap SOLSTICE - SANDLAKE_5: 4 active, 1,633.7 MW of 4 filed
- Tap Solstice to Bottlebrush: 5 active, 1,513.2 MW of 5 filed
- TNCENTRY1_1: 3 active, 763.2 MW of 3 filed
- Tap Coyanosa - Blair Lake Sub: 2 active, 605.3 MW of 2 filed
- Tap # HOLIDAY SUB TNP - # SOAPTREE TNP: 2 active, 402.3 MW of 2 filed
- LEON_CRK: 2 active, 401.4 MW of 2 filed
- Lynx: 4 active, 363.4 MW of 4 filed
- 860 GIRVINSW: 3 active, 317 MW of 3 filed
- TNCENTRY2_1: 2 active, 303.6 MW of 2 filed