Tap Solstice () - Bakersfield () Double circuit line substation interconnection queue

3 active projects totalling 3,008.3 MW in the ERCOT queue.

3active projects
3,008.3active MW
3total filed
Queue IDProjectkVMWResourceStatus
30INR0084 Gravitas I Natural Gas 345 1,247 Gas SS Completed, FIS Started, No IA
30INR0083 Gravitas I Solar 345 1,124.8 Solar SS Completed, FIS Started, No IA
30INR0085 Gravitas I Wind 345 636.5 Wind SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.