Barracks Road

Named in 1 PJM planning document for 1 project, on December 5, 2023.

Work described at itdescribed as
DOMzone
230kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

Part of a named transmission project: 2022 Window 3 South Cluster ($1,265.85M).

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
2022W3 – Recommended Solutions: South Cluster
B3800.360 – B3800.372
Not printed $183.49 M 6/1/2028 Not printed 2023-12-05
TEAC

Other substations in this project

“2022W3 – Recommended Solutions: South Cluster” also names 8 other substations, with what the most recent document says about each.

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $183.49 M → $46.53 M 2023-12-05 2025-05-06
Cost estimate
prior value printed on the same page
$70.14 M → $46.53 M 2025-05-06 2025-05-06
In-service date 6/1/2028 → 12/1/2028 2023-12-05 2025-05-06

Every mention

DateDocumentProjectWhat the document says about it
2023-12-05 TEAC
Item 15 - Reliability Analysis Update 2022 Window 3 p. 31
2022W3 – Recommended Solutions: South Cluster “Relay resets/revisions at the following substations: – Hollymeade, Proffit, Barracks Road, Crozet”
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first