Proffit
Named in 1 PJM planning document for 1 project, on December 5, 2023.
Work described at itdescribed as
DOMzone
—kV as printed
1mentions
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
Part of a named transmission project: 2022 Window 3 South Cluster ($1,265.85M).
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| 2022W3 – Recommended Solutions: South Cluster B3800.360 – B3800.372 |
Not printed | $183.49 M | 6/1/2028 | Not printed | 2023-12-05 TEAC |
Other substations in this project
“2022W3 – Recommended Solutions: South Cluster” also names 8 other substations, with what the most recent document says about each.
- Barracks Road DOM Work described at it — “Relay resets/revisions at the following substations: – Hollymeade, Proffit, Barracks Road, Crozet” (p. 31)
- Charlottesville DOM Work described at it — “Terminal equipment upgrades at the following substations: – Charlottesville for Lines #2054, #233 & #291 rebuilds” (p. 31)
- Crozet DOM Work described at it — “Relay resets/revisions at the following substations: – Hollymeade, Proffit, Barracks Road, Crozet” (p. 31)
- Dooms DOM Not stated — “Terminal equipment upgrades at the following substations: – Dooms for #233 & #291 rebuilds” (p. 31)
- Hollymeade DOM Work described at it — “Relay resets/revisions at the following substations: – Hollymeade” (p. 31)
- Hollymeade Junction DOM Not stated
- Hydraulic Rd DOM Not stated — “Terminal equipment upgrades at the following substations: – Hydraulic Rd for #233 & #291 rebuilds” (p. 31)
- Proffit DP DOM Not stated
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate | $183.49 M → $46.53 M | 2023-12-05 | 2025-05-06 |
| Cost estimate prior value printed on the same page |
$70.14 M → $46.53 M | 2025-05-06 | 2025-05-06 |
| In-service date | 6/1/2028 → 12/1/2028 | 2023-12-05 | 2025-05-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2023-12-05 | TEAC Item 15 - Reliability Analysis Update 2022 Window 3 p. 31 |
2022W3 – Recommended Solutions: South Cluster | “Relay resets/revisions at the following substations: – Hollymeade, Proffit” |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation", or when a PJM document prints a rename for the same project (src/ingest/rtepAliases.json; the entry lists its old names).
- role is "new" only where a cited document phrase calls the substation new, describes constructing it, or calls it proposed (graded by src/lib/roleBasis.js), "existing" where a phrase describes work at it, otherwise "unknown".
- expansion is set on a substation that is not "new" where a cited phrase describes a new voltage level, a new or expanded yard, bus or bay, or a named load connected to it (graded by src/lib/expansionBasis.js). It reproduces what the document describes and adds nothing to it.
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.