Substation Scout

Wattsville Substation

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Not stateddescribed as
Zone not identifiedzone
—kV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
6745/46 69kV Chincoteague Cable
ODEC-2023-02 · s3188.1
Engineering $6 M 12/30/2027 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
ODEC local plan submission for 2024 RTEP p. 5
6745/46 69kV Chincoteague Cable No role wording
2024-10-08 TEAC
Informational Only - ODEC Local Plan submission of supplemental project 2024 p. 5
6745/46 69kV Chincoteague Cable No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this