Septa substation interconnection queue

2 active projects totaling 336.4 MW in the PJM queue, plus 2 with terminal status (shown grayed).

4 PJM queue filings name Septa as the point of interconnection, all in VA.

Target commercial operation dates as filed run from Jan 2023 to Aug 2031 (4 filings).

Transmission owner as filed: Dominion (1 filing).

2active projects
336.4active MW
4total filed
Queue IDProjectkVMWResourceStatusTarget COD
AI1-017 Septa 500 kV 500 300 Battery Withdrawn Dec 2026
C01-1372 Septa 500 kV 500 200 Battery Withdrawn Aug 2031
AC1-161 Cavalier 500 168.2 Solar In Service Jan 2023
AC2-141 Sycamore Cross Solar 500 168.2 Solar Under Construction Apr 2026

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Septa (DOM, 4 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes at this substation

2 changes to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-10-19AC2-141Status changen/a Engineering and Procurement → Under Construction
2026-09-28C01-1372Terminal status200 Active → Withdrawn

Other PJM queue substations in Surry County, VA

All 43 PJM queue filings in Surry County, VA.

Other PJM queue substations in Isle of Wight County, VA

All 25 PJM queue filings in Isle of Wight County, VA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first