Substation Scout

Septa substation interconnection queue

3 active projects totalling 536.4 MW in the PJM queue, plus 1 with terminal status (shown greyed).

3active projects
536.4active MW
4total filed
Queue IDProjectkVMWResourceStatus
AI1-017 Septa 500 kV 500 300 Battery Withdrawn
C01-1372 Septa 500 kV 500 200 Battery Active
AC1-161 Cavalier 500 168.2 Solar In Service
AC2-141 Sycamore Cross Solar 500 168.2 Solar Engineering and Procurement

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.