Smithfield-Surry substation interconnection queue

1 active project totalling 79.2 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
79.2active MW
2total filed
Queue IDProjectkVMWResourceStatus
AB2-042 Smithfield-Surry 230kV 230 89 Solar Withdrawn
AH1-216 Smithfield-Surry 230 kV 230 79.2 Hybrid Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.