Hopewell-Surry substation interconnection queue

4 active projects totalling 325.8 MW in the PJM queue, plus 11 with terminal status (shown greyed).

4active projects
325.8active MW
15total filed
Queue IDProjectkVMWResourceStatus
AE2-270 Hopewell-Surry 230 kV 230 150 Hybrid Withdrawn
AB2-190 Fort Powhatan Solar 230 105 Solar In Service
AD1-025 Spring Grove Solar II 230 94.2 Solar In Service
AD1-151 Wild Indigo Solar 230 90 Solar Pending Termination
AB2-134 Colonial Trail West Solar 230 71.8 Solar In Service
AA2-177 Fort Powhatan Solar 230 56 Solar Withdrawn
AC1-216 Spring Grove I Solar 230 54.8 Solar In Service
AD2-008 Hopewell-Surry 230 kV 230 16.4 Solar Withdrawn
AG1-171 Hopewell-Surry 230kV 230 12 Solar Withdrawn
AG1-172 Hopewell-Surry 230 kV 230 12 Solar Withdrawn
AG1-173 Hopewell-Surry 230 kV 230 12 Solar Withdrawn
AG1-174 Hopewell-Surry 230 kV 230 12 Solar Withdrawn
AG1-175 Hopewell-Surry 230 kV 230 12 Solar Withdrawn
AD2-007 Hopewell-Surry 230 kV 230 4.5 Solar Withdrawn
AG1-009 Hopewell-Surry 230kV 230 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.