Substation Scout

Surry-Hopewell substation interconnection queue

1 active project totaling 89 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Surry-Hopewell as the point of interconnection, all in Surry County, VA.

Target commercial operation dates as filed run from Oct 2021 to Sep 2028 (2 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: Dominion (1 filing).

1active projects
89active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AF2-304 Bear Island Solar 230 89 Hybrid Engineering and Procurement Sep 2028
AF2-065 Surry-Hopewell 230 kV 230 76.5 Solar Withdrawn Oct 2021

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Surry County, VA

All 43 PJM queue filings in Surry County, VA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first