Substation Scout

Surry-Hopewell substation interconnection queue

1 active project totalling 89 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
89active MW
2total filed
Queue IDProjectkVMWResourceStatus
AF2-304 Bear Island Solar 230 89 Hybrid Engineering and Procurement
AF2-065 Surry-Hopewell 230 kV 230 76.5 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.