Mount Pleasant

In the 2025 MISO Transmission Expansion Plan (MTEP25), project 50166 of American Transmission Company, MISO West region.

Not printedstate
—kV as printed
$117.0Mestimated cost, as printed
1/1/2027in service, as printed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Racine County, DIC, Mount Pleasant Substation Expansion” — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50166, p.148

Project50166: “Racine County, DIC, Mount Pleasant Substation Expansion” (p.148)
Transmission ownerAmerican Transmission Company (ATC)
CategoryLoad Growth
Expedited Project ReviewYes, as the report marks it

The MTEP report prints no county for this substation.

Source: MTEP25 Report (2025 MISO Transmission Expansion Plan), approved by the MISO Board of Directors December 11, 2025; 428 of its 432 Appendix A projects are printed by name. Retrieved 2026-11-21; stations reviewed by hand 2026-11-21.