Substation Scout

Moonshine Solar Bootleg

In the 2025 MISO Transmission Expansion Plan (MTEP25), project 25018 of Ameren Illinois, MISO Central region.

ILstate, from the owner’s name
138kV as printed
$8.0Mestimated cost, as printed
12/1/2025in service, as printed

Described as new. The quoted wording calls this substation new. “New Moonshine Solar Bootleg 138 kV switching station (J1382)” — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 25018, p.57

Project25018: “New Moonshine Solar Bootleg 138 kV switching station (J1382)” (p.57)
Transmission ownerAmeren Illinois (AMIL)
CategoryNot printed
Expedited Project ReviewNot marked

Note. The project is the generator interconnection for MISO queue position J1382, as the project name prints it.

The MTEP report prints no county for this substation.

Location

Clark County, IL

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: No point. EDPR's April 2025 project layout map draws the developer's "Project Substation" near Oak Point, Clark County, but not Ameren's switching station; the switching station's own site is not printed.

Note: Timing: MTEP25 prints an in-service date of 12/1/2025, but EDPR told Clark County on 2025-06-10 that construction was "expected to start after this year's harvest and hoping to be completed at the end of 2026 and operational by 2027", and its fact sheet gives estimated commercial operation 2026. Capacity: the queue lists 150 MW; the EDPR fact sheet says 200 MW. Location caveat: the queue county is the request's county; the project area (Johnson Township, near Oak Point) lies 1-3 km east of the Clark/Cumberland county line (Census: -88.00 Clark, -88.01 Cumberland at 39.2 N), and the switching station's own parcel is not printed.

Sources: MISO MTEP25 Report (2025 MISO Transmission Expansion Plan), approved by the MISO Board 2025-12-11 (December 2025), p.57 · MISO interconnection queue request J1382 (Hutsonville - Neoga 138 kV Line tap), as listed by interconnection.fyi (queue date 2019-04-29), project record · Clark County, Illinois, minutes of the public hearing on solar projects (Moonshine Solar Park) (2025-06-10), p.1 · EDP Renewables, Moonshine Solar Park fact sheet (Clark County, Illinois) (2025-06), p.1 · EDP Renewables, Moonshine Solar Park open house posters, Project Layout map (map dated 2025-04-03), PDF p.7. Researched by Substation Scout; checked November 21, 2026.

Generation interconnection requests filed in Clark, IL: MISO queue, 9 active of 10. Same county, not the same substation.

Source: MTEP25 Report (2025 MISO Transmission Expansion Plan), approved by the MISO Board of Directors December 11, 2025; 428 of its 432 Appendix A projects are printed by name. Retrieved 2026-11-21; stations reviewed by hand 2026-11-21.