Substation Scout

Richland

In the 2025 MISO Transmission Expansion Plan (MTEP25), project 50345 of Duke Energy Corporation, MISO Central region.

Not printedstate
69kV as printed
$11.7Mestimated cost, as printed
10/18/2030in service, as printed

Described as new. The quoted wording calls this substation new. “New WVPA Richland 69 kV ring bus” — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50345, p.66

Project50345: “New WVPA Richland 69 kV ring bus” (p.66)
Transmission ownerDuke Energy Corporation (DEI)
CategoryLocal Reliability
Expedited Project ReviewNot marked

Note. The project name prints “WVPA Richland”: Duke Energy Indiana’s project for a Wabash Valley Power station.

The MTEP report prints no county for this substation.

Source: MTEP25 Report (2025 MISO Transmission Expansion Plan), approved by the MISO Board of Directors December 11, 2025; 428 of its 432 Appendix A projects are printed by name. Retrieved 2026-11-21; stations reviewed by hand 2026-11-21.

Before relying on any of this