War Eagle
In the 2025 MISO Transmission Expansion Plan (MTEP25), project 50360 of Entergy Texas, Inc., MISO South region.
Described as new. The quoted wording calls this substation new. “War Eagle 138 kV: Construct New Substation and Lines” — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50360, p.136
| Project | 50360: “War Eagle 138 kV: Construct New Substation and Lines” (p.136) |
|---|---|
| Transmission owner | Entergy Texas, Inc. (ETI) |
| Category | Not printed |
| Expedited Project Review | Not marked |
The MTEP report prints no county for this substation.
Location
Montgomery County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. Two printed placements in words: MTEP25 "approximately 0.3 miles north of the Oak Ridge 138 kV substation" and Entergy "approximately 2.5 miles southeast of the intersection of IH 45 and SH 242". Entergy's open-house notice map (2026-01-16) draws a "Proposed Substation Site Boundary" in an inset near Oak Ridge North; not georeferenced here. Not in OSM or HIFLD by name.
Note: The parent table had no in-service date printed; MTEP25's project figure (p.136) prints "Expected ISD 6/1/2029" and cost $110M. Entergy says the final route "will be determined by the Public Utility Commission of Texas" (no CCN docket number printed yet).
Sources: MISO MTEP25 Report (approved by the MISO Board of Directors 2025-12-11) (December 2025), p.136 · Entergy Texas, Forest to War Eagle to Porter 138 kV Transmission Line Project (n/a (retrieved 2026-11-21)), project page; listed on entergytexas.com/transmission as · Entergy Texas, Forest to War Eagle to Porter 138 kV Transmission Line Project brochure (n/a (open house 2026)), p.1-2 · Entergy Texas, Forest to War Eagle to Porter 138 kV, Preliminary Alternative Route Segments (open house notice map) (2026-01-16), single sheet. Researched by Substation Scout; checked November 21, 2026.
Generation interconnection requests filed in Montgomery, TX: ERCOT queue, 1 active of 1 · MISO queue, 2 active of 4. Same county, not the same substation.
Source: MTEP25 Report (2025 MISO Transmission Expansion Plan), approved by the MISO Board of Directors December 11, 2025; 428 of its 432 Appendix A projects are printed by name. Retrieved 2026-11-21; stations reviewed by hand 2026-11-21.
Before relying on any of this
- The MTEP report prints no state or county column. A state shown here is the one printed in the transmission owner’s name (“Ameren Missouri”, “Entergy Texas”); for owners that serve several states it is left blank, as is a county no source prints for the station.
- The report prints 428 of the 432 projects in its Appendix A by name; a project it does not print is not read here, and a substation built under a project whose name does not describe a new station is not listed.
- An in-service date and a cost are the ones the report prints (cost in millions of dollars, as estimated), not a construction schedule.
- A few projects are printed only as a heading over a map image (baseline reliability projects such as Pond Creek and War Eagle); their in-service date and cost appear in the image, not the report’s text, and are not shown here.