Rhodair
In the 2025 MISO Transmission Expansion Plan (MTEP25), project 50199 of Entergy Texas, Inc., MISO South region.
Described as new. The quoted wording calls this substation new. “Rhodair 230 kV New Substation and Transmission Lines” — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50199, p.137
| Project | 50199: “Rhodair 230 kV New Substation and Transmission Lines” (p.137) |
|---|---|
| Transmission owner | Entergy Texas, Inc. (ETI) |
| Category | Load Growth |
| Expedited Project Review | Yes, as the report marks it |
The MTEP report prints no county for this substation.
Location
Jefferson County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. The progress reports print the county only; the MTEP25 map shows a new-station dot south of Port Arthur at a scale too small for a point. Not in OSM or HIFLD by name (OSM extract 2026-11-20).
Note: Schedule only: MTEP25 prints ISD 8/26/2025; the EPR deck gave 7/1/2025 and the PUCT reports a construction finish of 06/15/25 (still unchanged in the July 2025 report, with no energized date). No source found that it is in service.
Sources: MISO MTEP25 Report (approved by the MISO Board of Directors 2025-12-11) (December 2025), p.137 · Entergy Texas, Inc. Transmission Construction Progress Report for November 2024 (PUCT Project No. 56006, item 356) (filed 2024-11-15), p.2 · Entergy Texas, Inc. Construction Progress Report, July 2025 (PUCT Project No. 57477, item 207) (filed 2025-07-14), project TSK899 · MISO MTEP25 Expedited Project Review: Rhodair, Sabine Pass and South China Substations (South Technical Study Task Force) (2024-09-16), slides 3-4. Researched by Substation Scout; checked November 21, 2026.
Generation interconnection requests filed in Jefferson, TX: ERCOT queue, 1 active of 1 · MISO queue, 2 active of 14. Same county, not the same substation.
Source: MTEP25 Report (2025 MISO Transmission Expansion Plan), approved by the MISO Board of Directors December 11, 2025; 428 of its 432 Appendix A projects are printed by name. Retrieved 2026-11-21; stations reviewed by hand 2026-11-21.
Before relying on any of this
- The MTEP report prints no state or county column. A state shown here is the one printed in the transmission owner’s name (“Ameren Missouri”, “Entergy Texas”); for owners that serve several states it is left blank, as is a county no source prints for the station.
- The report prints 428 of the 432 projects in its Appendix A by name; a project it does not print is not read here, and a substation built under a project whose name does not describe a new station is not listed.
- An in-service date and a cost are the ones the report prints (cost in millions of dollars, as estimated), not a construction schedule.
- A few projects are printed only as a heading over a map image (baseline reliability projects such as Pond Creek and War Eagle); their in-service date and cost appear in the image, not the report’s text, and are not shown here.