Bluepoint

In the 2025 MISO Transmission Expansion Plan (MTEP25), project 50546 of Entergy Louisiana LLC, MISO South region.

LAstate, from the owner’s name
230kV as printed
$59.6Mestimated cost, as printed
8/1/2027in service, as printed

Described as new. The quoted wording calls this substation new. “Bluepoint 230 kV New Substation and line Cut-ins” — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50546, p.123

Project50546: “Bluepoint 230 kV New Substation and line Cut-ins” (p.123)
Transmission ownerEntergy Louisiana LLC (ELL)
CategoryLoad Growth
Expedited Project ReviewYes, as the report marks it

The MTEP report prints no county for this substation.

Source: MTEP25 Report (2025 MISO Transmission Expansion Plan), approved by the MISO Board of Directors December 11, 2025; 428 of its 432 Appendix A projects are printed by name. Retrieved 2026-11-21; stations reviewed by hand 2026-11-21.