Cecil, MD interconnection queue

10 active projects totalling 1,967.7 MW in the PJM queue, plus 15 with terminal status (shown greyed).

10active projects
1,967.7active MW
25total filed
Queue IDProjectkVMWResourceStatus
Y1-065 Wildcat Point 500 805 Gas In Service
A29 Rock Springs n/r 465 Gas In Service
A30 Rock Springs n/r 465 Gas In Service
X1-015 Kenney-Rock Springs 500kV 500 360 Not reported Withdrawn
Y3-102 Wildcat Point 500 135 Gas In Service
X4-024 Rock Springs 500kV 500 109 Not reported Withdrawn
AI2-307 Colora 230 kV 230 60.5 Battery Withdrawn
AD2-167 Wildcat Point 500 52 Gas In Service
AF2-208 Colora 230 kV 230 40.3 Battery Withdrawn
R20 Rock Springs Units 3 & 4 n/r 20 Gas In Service
AB2-182 Townsend 25kV 25 14 Solar Withdrawn
U4-015 Rocks Springs 1 & 2 500 8.7 Gas In Service
AC2-018 Rock Springs Units #3 & #4 500 8 Gas In Service
AE2-061 Rock Springs Unit #1 and Unit #2 500 7 Gas In Service
AB2-056 Colora 34.5kV 34.5 3.8 Solar Withdrawn
AB2-168 Crouse Solar Project 34.5 3.8 Solar Withdrawn
Z1-041 Rock Springs Units #1 & #2 500 2 Gas In Service
AB2-113 Cecil County 1 n/r 0.8 Solar Withdrawn
AB2-114 Cecil County 2 n/r 0.8 Solar Withdrawn
AB2-115 Cecil County 3 n/r 0.8 Solar Withdrawn
AB2-116 Cecil County 4 n/r 0.8 Solar Withdrawn
AB2-117 Cecil County 5 n/r 0.8 Solar Withdrawn
AB2-118 Cecil County 6 n/r 0.8 Solar Withdrawn
AI2-054 Rock Springs 500 kV 500 0 Battery Withdrawn
U3-004 Cecil County Landfill n/r 0 Gas Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.