Substation Scout

New Castle Solar

PJM queue ID AB2-179

New Castle Solar (AB2-179) is listed in the PJM interconnection queue as a 37.6 MW solar project in New Castle County, DE. The filing names Townsend as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 16, 2022.

Queue IDAB2-179
Project nameNew Castle Solar
Status (as published)In Service
SubstationTownsend
Point of interconnectionTownsend 138kV
CountyNew Castle
StateDE
Voltage138 kV
Capacity37.6 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2022-12-16
Source datasetserial

Same substation and county

Townsend substation: 3 requests in the PJM queue, 1 active totaling 37.6 MW.

Queue IDProjectMWResourceStatus
AB2-182Townsend 25kV14SolarWithdrawn
W3-086Townsend 138kV3.8SolarWithdrawn

New Castle, DE: 65 requests in the PJM queue, 31 active totaling 1,405.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy50
MW capacity37.6
MFO50

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first