Stony Creek Solar (AF2-221) is listed in the PJM interconnection queue as a 6.3 MW solar project in Somerset County, PA. The filing names Scalp Level as its point of interconnection. PJM lists its status as “Suspended”, with a target commercial operation date of October 1, 2025.

Queue IDAF2-221
Project nameStony Creek Solar
Status (as published)Suspended
SubstationScalp Level
Point of interconnectionScalp Level 22.9 kV
CountySomerset
StatePA
Voltage22.9 kV
Capacity6.3 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2025-10-01
Source datasetserial

Same substation and county

Scalp Level substation: 6 requests in the PJM queue, 1 active totaling 6.3 MW.

Queue IDProjectMWResourceStatus
I15Scalp Level 115kV9.9GasWithdrawn
AG1-241Scalp Level 23 kV6.5SolarWithdrawn
AH2-360Scalp Level 23 kV6.5SolarWithdrawn
AF1-218Scalp Level 23 kV6.3SolarWithdrawn
AG1-033Scalp Level 23 kV3.2SolarWithdrawn

Somerset, PA: 107 requests in the PJM queue, 25 active totaling 286.9 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy15
MW capacity6.3
MFO15

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first