Payne substation interconnection queue
2 active projects totaling 30 MW in the PJM queue, plus 2 with terminal status (shown grayed).
Target commercial operation dates as filed run from Nov 2019 to Dec 2025 (4 filings).
Transmission owner as filed: AEP (1 filing).
2active projects
30active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AC2-181 | Payne 69kV | 69 | 19 | Solar | Withdrawn | Nov 2019 |
| AD1-119 | Timber Road Solar Park | 69 | 19 | Solar | In Service | Nov 2023 |
| AI2-117 | Payne 69 kV | 69 | 12 | Solar | Withdrawn | Jun 2023 |
| AG2-406 | Payne 69 kV | 69 | 11 | Solar | Active | Dec 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Randolph County, IN
- Losantville: 6 active, 410.5 MW of 9 filed
- Desoto - Tanners Creek: 2 active, 301.5 MW of 3 filed
- Marysville: 4 active, 280.8 MW of 9 filed
- Randolph - Hodgin: 1 active, 90 MW of 3 filed
- Bluff Point - Randolph: 2 active, 80 MW of 2 filed
- Bluff Point-Randolph: 1 active, 42 MW of 3 filed
- Desoto: 2 active, 26 MW of 6 filed
- Desoto-Tanners Creek: 1 active, 26 MW of 5 filed
- Desoto-Tanners Creek #1: 1 active, 26 MW of 3 filed
Other PJM queue substations in Paulding County, OH
- Maddox Creek-RP Mone: 2 active, 280 MW of 4 filed
- Logtown: 3 active, 59.8 MW of 4 filed
- Haviland: 3 active, 33.8 MW of 5 filed
- Lincoln-Sterling: 1 active, 30 MW of 3 filed
- Haviland - Milan: 1 active, 30 MW of 2 filed
- Timber Switch: 1 active, 20 MW of 3 filed
Site Scanner