Substation Scout

Maddox Creek-RP Mone substation interconnection queue

2 active projects totaling 280 MW in the PJM queue, plus 2 with terminal status (shown grayed).

4 PJM queue filings name Maddox Creek-RP Mone as the point of interconnection, all in OH.

Target commercial operation dates as filed run from Dec 2016 to Feb 2030 (4 filings). 2 active filings target a date after November 27, 2026.

Transmission owner as filed: AEP (2 filings).

2active projects
280active MW
4total filed
Queue IDProjectkVMWResourceStatusTarget COD
AG1-410 Butterfly Meadows 345 180 Solar EP Feb 2030
AG1-411 Butterfly Meadows 345 100 Battery EP Feb 2030
AI2-366 Maddox Creek-RP Mone 345 kV 345 93.6 Solar Withdrawn Sep 2024
T130 Maddox Creek-RP Mone 345 kV 345 60 Wind Withdrawn Dec 2016

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Van Wert County, OH

All 26 PJM queue filings in Van Wert County, OH.

Other PJM queue substations in Paulding County, OH

All 28 PJM queue filings in Paulding County, OH.

Site Scanner