3 active projects totalling 485.5 MW in the PJM queue.

3active projects
485.5active MW
3total filed
Queue IDProjectkVMWResourceStatus
C01-1404 Desoto - Tanners Creek 345 kV 345 200 Battery Active
C01-1202 Desoto - Tanners Creek 345 kV 345 184 Solar Active
C01-1418 Desoto - Tanners Creek 345 kV 345 101.5 Wind Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.