Substation Scout

Desoto - Tanners Creek substation interconnection queue

2 active projects totaling 301.5 MW in the PJM queue, plus 1 with terminal status (shown grayed).

3 PJM queue filings name Desoto - Tanners Creek as the point of interconnection, all in IN.

Target commercial operation dates as filed run from Apr 2026 to Dec 2030 (3 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: AEP (3 filings).

2active projects
301.5active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1404 Desoto - Tanners Creek 345 kV 345 200 Battery Active Dec 2030
C01-1202 Desoto - Tanners Creek 345 kV 345 184 Solar Withdrawn Dec 2030
C01-1418 Desoto - Tanners Creek 345 kV 345 101.5 Wind Active Apr 2026

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Tracked changes at this substation

1 change to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-10-05C01-1202Terminal status184 Active → Withdrawn

Same name on other Substation Scout pages

Other sources that print a substation named “Desoto - Tanners Creek” in IN. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each.

Other PJM queue substations in Wayne County, IN

No other substation in Wayne County, IN is named as a point of interconnection in the PJM queue.

All 5 PJM queue filings in Wayne County, IN.

Other PJM queue substations in Randolph County, IN

All 43 PJM queue filings in Randolph County, IN.