PJM queue ID AD1-119

Timber Road Solar Park (AD1-119) is listed in the PJM interconnection queue as a 19 MW solar project in Paulding County, OH. The filing names Payne as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of November 30, 2023.

Queue IDAD1-119
Project nameTimber Road Solar Park
Status (as published)In Service
SubstationPayne
Point of interconnectionPayne 69 kV
CountyPaulding
StateOH
Voltage69 kV
Capacity19 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2023-11-30
Source datasetserial

Same substation and county

Payne substation: 4 requests in the PJM queue, 2 active totaling 30 MW.

Queue IDProjectMWResourceStatus
AG2-406Payne 69 kV11SolarActive
AC2-181Payne 69kV19SolarWithdrawn
AI2-117Payne 69 kV12SolarWithdrawn

Paulding, OH: 28 requests in the PJM queue, 12 active totaling 250.2 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy49.9
MW capacity18.96
MFO49.9

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.