Bluff Point-Randolph substation interconnection queue

1 active project totaling 42 MW in the PJM queue, plus 2 with terminal status (shown grayed).

3 PJM queue filings name Bluff Point-Randolph as the point of interconnection, all in Randolph County, IN.

Target commercial operation dates as filed run from Oct 2021 to Jul 2028 (3 filings). 1 active filing targets a date after November 27, 2026.

1active projects
42active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE2-219 Riverstart Solar Park V 138 42 Solar Engineering and Procurement Jul 2028
AI2-112 Bluff Point-Randolph 138 kV 138 42 Solar Withdrawn Oct 2026
AE1-137 Bluff Point-Randolph n/r 38 Solar Withdrawn Oct 2021

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Same name on other Substation Scout pages

Other sources that print a substation named “Bluff Point-Randolph” in IN. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each.

Other PJM queue substations in Randolph County, IN

All 43 PJM queue filings in Randolph County, IN.