Paulding, OH interconnection queue

13 active projects totalling 539.5 MW in the PJM queue, plus 15 with terminal status (shown greyed).

13active projects
539.5active MW
28total filed
Queue IDProjectkVMWResourceStatus
C01-2029 Haviland - Timber Switch 138 kV & Logtown - North Delphos 138 kV 138 289.3 Gas Active
AI1-104 Timber Road 138 kV 138 86.7 Solar Withdrawn
T130 Maddox Creek-RP Mone 345 kV 345 60 Wind Withdrawn
AI2-102 Lincoln-Sterling 138kV 138 46.8 Wind Withdrawn
C01-1420 Lincoln - Sterling 138 kV 138 46.6 Wind Active
AI2-101 Haviland - Milan 138kV 138 42.6 Wind Withdrawn
AI2-092 Logtown 138 kV 138 40.3 Wind Withdrawn
R49 Timber Road II WF 138 30 Wind In Service
S117 Haviland 138kV 138 30 Wind Withdrawn
S118 North Delphos 138kV 138 30 Wind Withdrawn
T131 Timber Road III 138 30 Wind In Service
AG1-369 Timber Road Solar Park III 138 29.9 Solar Engineering and Procurement
AH1-522 Timber Switch 138 kV 138 28.2 Solar Withdrawn
AI2-091 Lincoln-Sterling 138kV 138 22.7 Wind Withdrawn
AF2-376 Timber Road II WF 138 20 Battery EP
AF2-377 Timber Road Storage III 138 20 Battery Engineering and Procurement
AE1-245 Grover Hill Wind Project 138 19.5 Wind Partially in Service - Under Construction
V1-012 Trishe Wind Ohio, LLC 138 19.5 Wind Withdrawn
AD1-119 Timber Road Solar Park 69 19 Solar In Service
AF2-186 South Cecil 69 kV 69 18.9 Solar Withdrawn
V1-011 Trishe Wind Ohio, LLC 138 13 Wind In Service
AI2-117 Payne 69 kV 69 12 Solar Withdrawn
AG2-406 Payne 69 kV 69 11 Solar Active
AC1-173 Timber Road IV Wind Farm (Southern Phase) 138 9.9 Wind In Service
R48 Paulding aka Project R48 69 9.7 Wind Withdrawn
AC1-176 Timber Switch 138kV 138 7.6 Wind Withdrawn
U2-026 Antwerp 69kV 69 3.9 Wind Withdrawn
AF2-103 Northwest Ohio Wind 138 1.3 Hybrid In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.