Losantville substation interconnection queue
6 active projects totalling 410.5 MW in the PJM queue, plus 3 with terminal status (shown greyed).
6active projects
410.5active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1386 | Losantville 345 kV | 345 | 200 | Battery | Active |
| AE2-220 | Riverstart Solar Park II | 345 | 52.5 | Solar | Engineering and Procurement |
| AI2-120 | Losantville 345 kV | 345 | 52.5 | Solar | Withdrawn |
| AI2-119 | Losantville 345 kV | 345 | 48 | Solar | Withdrawn |
| AI2-110 | Losantville 345 kV | 345 | 46 | Solar | Withdrawn |
| AG2-401 | Losantville 345 kV | 345 | 44 | Solar | Active |
| AC1-174 | Riverstart Solar Park | 345 | 38 | Solar | In Service |
| AC1-175 | Riverstart Solar Park | 345 | 38 | Solar | In Service |
| AC2-090 | Riverstart Solar Park III | 345 | 38 | Solar | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.