Substation Scout

Desoto substation interconnection queue

2 active projects totaling 26 MW in the PJM queue, plus 4 with terminal status (shown grayed).

6 PJM queue filings name Desoto as the point of interconnection, all in IN.

Target commercial operation dates as filed run from Dec 2013 to May 2027 (6 filings). 2 active filings target a date after November 27, 2026.

Transmission owner as filed: AEP (1 filing).

2active projects
26active MW
6total filed
Queue IDProjectkVMWResourceStatusTarget COD
AF1-298 Desoto 345 kV 345 84 Solar Withdrawn Oct 2023
AF2-173 Esker Solar Park 345 84 Solar Withdrawn Oct 2023
AI2-115 Desoto 345 kV 345 84 Solar Withdrawn Oct 2026
V3-053 Desoto 138kV 138 19.5 Wind Withdrawn Dec 2013
AE1-209 Headwaters Wind Farm III 345 13 Wind Suspended May 2027
AE1-210 Headwaters Wind Farm III 345 13 Wind Suspended May 2027

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Desoto (AEP, 5 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Other PJM queue substations in Delaware County, IN

All 22 PJM queue filings in Delaware County, IN.

Other PJM queue substations in Randolph County, IN