Randolph - Hodgin substation interconnection queue

1 active project totalling 90 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
90active MW
3total filed
Queue IDProjectkVMWResourceStatus
AG2-637 Randolph - Hodgin 138 kV 138 90 Solar Active
AH1-432 Randolph - Hodgin 138 kV 138 60 Battery Withdrawn
AH1-337 Randolph - Hodgin 138 kV 138 39 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.