Oak Grove substation interconnection queue
6 active projects totalling 398.8 MW in the PJM queue, plus 3 with terminal status (shown greyed).
6active projects
398.8active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| B12_W02 | Oak Grove CT1 & CT2 | 138 | 300 | Gas | In Service |
| G30_W52 | Oak Grove CT1 & CT2 | 138 | 54 | Gas | In Service |
| AA2-131 | Oak Grove 138kV | 138 | 18 | Gas | In Service |
| Y2-054 | Oak Grove 138kV | 138 | 13.7 | Gas | In Service |
| AE1-124 | VSF Solar I | 34.5 | 13.3 | Solar | Withdrawn |
| AH1-398 | Oak Grove 22.9 kV | 22.9 | 11.7 | Solar | Withdrawn |
| AH1-637 | Oak Grove 34.5 kV | 34.5 | 9.6 | Solar | Active |
| B24 | Oak Grove 13.8kV | 13.8 | 6.8 | Gas | Withdrawn |
| H20 | Oak Grove 13.8kV | 13.8 | 3.5 | Gas | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.