Oak Grove - West Moreland substation interconnection queue

2 active projects totalling 220 MW in the PJM queue.

2active projects
220active MW
2total filed
Queue IDProjectkVMWResourceStatus
C01-1601 Oak Grove - West Moreland 230 kV 230 120 Solar Active
C01-1602 Oak Grove - West Moreland 230 kV 230 100 Battery Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.