Oak Grove – Saunders DP substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

2 PJM queue filings name Oak Grove – Saunders DP as the point of interconnection, all in Westmoreland County, VA.

Target commercial operation dates as filed run from Dec 2024 to Dec 2027 (2 filings).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AG2-526 Oak Grove – Saunders DP 230 kV 230 60 Solar Withdrawn Dec 2024
AI2-419 Oak Grove – Saunders DP 230 kV 230 25 Solar Withdrawn Dec 2027

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.