Evans Creek substation interconnection queue
3 active projects totaling 440 MW in the PJM queue.
3 PJM queue filings name Evans Creek as the point of interconnection, all in Mecklenburg County, VA.
Target commercial operation date as filed: Dec 2032 (3 filings). 3 active filings target a date after November 27, 2026.
Transmission owner as filed: Dominion (3 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| C01-1599 | Evans Creek 230kV | 230 | 200 | Battery | Active | Dec 2032 |
| C01-1597 | Evans Creek 230kV | 230 | 159 | Solar | Active | Dec 2032 |
| C01-1598 | Evans Creek 230kV | 230 | 81 | Solar | Active | Dec 2032 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
PJM planning mentions
A substation with the same name is named in PJM transmission planning materials: Evans Creek (DOM, 2 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Other PJM queue substations in Mecklenburg County, VA
- Palmer Springs: 2 active, 240 MW of 9 filed
- Chase City-Lunenburg: 2 active, 132.4 MW of 3 filed
- Briery-Clover: 1 active, 54 MW of 6 filed
- Buggs Island-Chase City: 3 active, 36 MW of 3 filed
- Gretna DP: 1 active, 19 MW of 2 filed
- Chase City: 1 active, 18.9 MW of 7 filed
- Boydton Plank Road: none active of 4 filed
- Beechwood DP-Palmer Springs: none active of 2 filed
- Boydton DP: none active of 2 filed
- Central VA- Chase City: none active of 2 filed
- Chase City-Drakes Branch: none active of 2 filed
- Kerr Dam - Buggs Island: none active of 2 filed
- Reedy Creek- Kinderton: none active of 2 filed