Chase City substation interconnection queue

1 active project totalling 18.9 MW in the PJM queue, plus 6 with terminal status (shown greyed).

1active projects
18.9active MW
7total filed
Queue IDProjectkVMWResourceStatus
AH1-450 Chase City 115kV 115 50 Battery Withdrawn
AB2-090 Chase City 34.5kV 34.5 23.8 Solar Withdrawn
AB2-043 Bluestone Farm Solar 115 18.9 Solar In Service
AC1-106 Chase City 115kV 115 15.7 Solar Withdrawn
AE2-258 Chase City 115 kV 115 14.1 Solar Withdrawn
AB2-176 Chase City 34.5kV 34.5 9.8 Solar Withdrawn
AG2-019 Chase City 12.5 kV 12.5 6 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.