Ohara
Named in 10 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
10projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Also printed as: O'Hara
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| CC - FAYETTEVILLE AREA TRANSMISSION NEEDS Build a new 500/230kV substation (Ashley Park) splitting the Ohara - Union City 500kV line. Install two 500/230kV auto transformers at the Ashley Park station. Build two new 230kV lines (6 miles each) from Ashley Park to the high side of the customer substations. The new lines will be built with bundled 200C 1351 ACSS Martin conductor. TEAMS 20018 · plan p.84 · zone 208 |
GPC | In the plan p.7 |
Apr 1, 2026 | No change | Ashley Park, Ohara, Union City |
| GTC: DRESDEN 500kV BUS EXPANSION GTC will expand and reconfigure the Dresden 500kV bus. Loop the O'Hara - Wansley 500kV line into the Dresden 500kV substation and allow for future Dresden - Talbot 500kV line termination. TEAMS 20273 · plan p.109 · zone 208 |
GTC | In the plan p.9 |
Dec 1, 2026 | No change | Dresden, Ohara, Talbot, Wansley |
| OHARA LINE PROTECTIVE RELAYING REPLACEMENT On the O'Hara - Wansley 500kV line, replace the protective relay panels at O'Hara associated with the 500kV line terminal facing Dresden. TEAMS 20668 · plan p.55 · zone 208 |
GPC | In the plan p.9 |
Dec 1, 2026 | No change | Ohara, Wansley |
| CC - TOMOCHICHI 500/230kV SOLUTION (NETWORK IMPROVEMENTS) Build the new Tomochichi 500/230kV station splitting the Ohara - Scherer 500kV line. Build two 230kV lines from the new Tomochichi substation to the new Towaliga River 230kV substation with bundled 200C 1351 ACSS Martin. One will be 6 miles, and one will be 5 miles. Also adjust the tap settings on the 500/230kV transformer to address high voltage concerns on the 230kV system. TEAMS 20717 · plan p.149 · zone 208 |
GPC | In the plan p.12 |
Sep 15, 2027 | Delayed within 2027 | Ohara, Scherer, Tomochichi, Towaliga River |
| OHARA 115kV BREAKER REPLACEMENT Replace breaker on the Ohara - Tara 115kV Line at the Ohara substation. TEAMS 21022 · plan p.62 · zone 208 |
GPC | In the plan p.9 |
Oct 1, 2026 | No change | Ohara, Tara |
| WANSLEY RELAY WORK AND NEW FIBER On the O'Hara - Wansley 500kV line, replace the protective relay panels at Wansley associated with the 500kV line terminal facing Dresden. TEAMS 21174 · plan p.112 · zone 208 |
GPC | In the plan p.9 |
Dec 1, 2026 | New project | Ohara, Wansley |
| CC - PROJECT SPEEDWAY (NETWORK IMPROVEMENTS) Construct a new 500/230kV substation and loop in the Ohara - Scherer 500kV line. Install two 500/230kV auto transformers and build two new 1-mile 230kV lines each to Speedway #1 and Speedway #2, utilizing 200C 1351 ACSS Martin. TEAMS 21332 · plan p.122 · zone 208 |
GPC | In the plan p.10 |
Jun 1, 2027 | New project | Hills Bridge, Ohara, Scherer, Speedway #1, Speedway #2 |
| GTC: SMARR 500kV TRANSMISSION SERVICE Construct the Rum Creek 500kV switching station. Loop in the existing Bonaire Primary - Scherer and O'Hara - Scherer 500kV lines. Terminate the new Big Smarr - Rum Creek 500kV line. Construct the new line using 100C (3) 1113 ACSR Bluejay conductor. TEAMS 21345 · plan p.167 · zone 214 |
GTC | In the plan p.13 |
Jun 1, 2028 | New project | Big Smarr, Ohara, Rum Creek, Scherer |
| HAMPTON AREA 115 TO 230kV LINE CONVERSIONS Convert Hampton – Ohara 115kV and Jonesboro – Ohara 115kV to create a new Jonesboro – Hampton 230kV line. Convert Hampton – South Griffin 115kV to 230kV operation. Loop in Jonesboro - Ohara 115kV through Bonanza so it is not radial. Install a new 230/115kV auto transformer at Jonesboro. TEAMS 21566 · plan p.169 · zone 208 |
GPC | In the plan p.13 |
Jun 1, 2028 | New project | Hampton, Jonesboro, Ohara, South Griffin |
| GTC: OHARA - SOUTH GRIFFIN 230kV LINE RECONDUCTOR Reconductor 23 miles of the Ohara - South Griffin 230kV line section using 200C 1351 ACSS Martin. TEAMS 21594 · plan p.209 · zone 208 |
GTC | In the plan p.16 |
Jun 1, 2029 | New project | Ohara, South Griffin |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.