Wansley
Named in 5 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
5projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| GTC: DRESDEN 500kV BUS EXPANSION GTC will expand and reconfigure the Dresden 500kV bus. Loop the O'Hara - Wansley 500kV line into the Dresden 500kV substation and allow for future Dresden - Talbot 500kV line termination. TEAMS 20273 · plan p.109 · zone 208 |
GTC | In the plan p.9 |
Dec 1, 2026 | No change | Dresden, Ohara, Talbot, Wansley |
| OHARA LINE PROTECTIVE RELAYING REPLACEMENT On the O'Hara - Wansley 500kV line, replace the protective relay panels at O'Hara associated with the 500kV line terminal facing Dresden. TEAMS 20668 · plan p.55 · zone 208 |
GPC | In the plan p.9 |
Dec 1, 2026 | No change | Ohara, Wansley |
| GTC: TENASKA - WANSLEY 500kV NEW LINE Construct 5 miles of 500kV line between Tenaska and Wansley. Make necessary accommodations at Tenaska for the line termination and reconfigure Wansley substation TEAMS 21123 · plan p.211 · zone 201 |
GTC | In the plan p.16 |
Jun 1, 2029 | No change | TENASKA, Wansley |
| WANSLEY RELAY WORK AND NEW FIBER On the O'Hara - Wansley 500kV line, replace the protective relay panels at Wansley associated with the 500kV line terminal facing Dresden. TEAMS 21174 · plan p.112 · zone 208 |
GPC | In the plan p.9 |
Dec 1, 2026 | New project | Ohara, Wansley |
| CAVENDER DRIVE - WANSLEY 500kV LINE Build a new 500kV line approximately 37 miles long from Cavender Drive to Wansley long with bundled (3) 100C Bluejay 1113. TEAMS 21496 · plan p.235 · zone 211 |
GPC | In the plan p.18 |
Jun 1, 2030 | New project | CAVENDER DRIVE, Wansley |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.