Hills Bridge
Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035), in Clayton County.
Described as new. The quoted wording calls this substation new. “Hills Bridge 500/230 kV Substation: Construction of a new substation in Clayton County to support both 500 kV and 230 kV transmission infrastructure.” — Georgia Power, Hills Bridge–Speedway 500 kV Transmission Project page, retrieved 2026-11-20
The plan names Hills Bridge as a line terminal (TEAMS 21582, 21674) and builds an unnamed new 500/230kV substation in TEAMS 21332 ("CC - PROJECT SPEEDWAY"); Georgia Power's page for that project names it.
County: “Hills Bridge 500/230 kV Substation: Construction of a new substation in Clayton County” — Georgia Power, Hills Bridge–Speedway 500 kV Transmission Project page, retrieved 2026-11-20. The plan itself prints no county column.
Location
33.3725, -84.3615 · Clayton County, GA · view on a map
Point published by the utility. The utility publishes this point, on a project map or in a filing. Accurate to about ±350 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: Printed by the sponsor: Georgia Power's Hills Bridge–Speedway project page embeds its project map's configuration, with a 10-vertex polygon titled "Hills Bridge Sub" (yellow fill, orange outline; first vertex 33.36999711, -84.36001776); the point is the mean of its vertices. All four printed line routes (OH Scherer 500 kV, OH Wansley 500 kV, Speedway #1 230 kV, Speedway #2) start at its edge. Web-map polygon, not a survey: the page says "MAP NOT BASED ON FIELD SURVEY DATA" and "Structure and Line Locations based on Pre-Engineering data and subject to change". Accuracy ±350 m is the polygon's own radius (farthest vertex 343 m from the mean).
Sources: Georgia Power, Hills Bridge–Speedway 500 kV Transmission Project page (n/a (retrieved 2026-11-20)), About the Project; Project Map · 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.122. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| HAMPTON - HILLS BRIDGE 230kV NEW LINE Build a 6 miles 230kV line from Hills Bridge to Hampton using 200C 1351 ACSS Martin conductor. TEAMS 21582 · plan p.170 · zone 208 |
GPC | In the plan p.13 |
Jun 1, 2028 | New project | Hampton, Hills Bridge |
| HILLS BRIDGE - SOUTH COWETA 230kV NEW LINE Build a 13 miles 230kV line from Hills Bridge to South Coweta using 200C 1351 ACSS Martin conductor. Install a second 230/115kV auto transformer at South Coweta. TEAMS 21674 · plan p.171 · zone 208 |
GPC | In the plan p.13 |
Jun 1, 2028 | New project | Hills Bridge, South Coweta |
| CC - PROJECT SPEEDWAY (NETWORK IMPROVEMENTS) Construct a new 500/230kV substation and loop in the Ohara - Scherer 500kV line. Install two 500/230kV auto transformers and build two new 1-mile 230kV lines each to Speedway #1 and Speedway #2, utilizing 200C 1351 ACSS Martin. TEAMS 21332 · plan p.122 · zone 208 |
GPC | In the plan p.10 |
Jun 1, 2027 | New project | Hills Bridge, Ohara, Scherer, Speedway #1, Speedway #2 |
Generation interconnection requests filed in Clayton, GA: Southern Company queue, 0 active of 2. Same county, not the same substation.
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.