Hampton
Named in 4 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTC, MEAGproject sponsor
4projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| HAMPTON AREA 115 TO 230kV LINE CONVERSIONS Convert Hampton – Ohara 115kV and Jonesboro – Ohara 115kV to create a new Jonesboro – Hampton 230kV line. Convert Hampton – South Griffin 115kV to 230kV operation. Loop in Jonesboro - Ohara 115kV through Bonanza so it is not radial. Install a new 230/115kV auto transformer at Jonesboro. TEAMS 21566 · plan p.169 · zone 208 |
GPC | In the plan p.13 |
Jun 1, 2028 | New project | Hampton, Jonesboro, Ohara, South Griffin |
| GTC: NEW HAMPTON 230/115kV SUB Construct a new 230/115kV substation next to the existing Hampton 115kV substation. TEAMS 21567 · plan p.166 · zone 208 |
GTC | In the plan p.13 |
Jun 1, 2028 | New project | Hampton, New Hampton |
| MEAG: BIG SOUTH GRIFFIN 230/115kV SUBSTATION Build a new 230/115kV substation and relocate all lines except for the South Coweta and Griffin #1 115kV lines from the existing South Griffin substation. Terminate the newly converted Hampton - South Griffin 230kV line. Install two 230/115kV auto transformers. TEAMS 21568 · plan p.175 · zone 208 |
MEAG | In the plan p.13 |
Jun 1, 2028 | New project | Big South Griffin, Hampton, South Griffin |
| HAMPTON - HILLS BRIDGE 230kV NEW LINE Build a 6 miles 230kV line from Hills Bridge to Hampton using 200C 1351 ACSS Martin conductor. TEAMS 21582 · plan p.170 · zone 208 |
GPC | In the plan p.13 |
Jun 1, 2028 | New project | Hampton, Hills Bridge |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.