Scherer

Named in 5 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
5projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
GTC: EAST WALTON 500/230kV PROJECT
GTC: - Construct the East Walton 500/230kV substation - Construct the Bostwick 230kV switching station - Construct the East Walton - Rockville 500kV line - Construct the Bethabara - East Walton 230kV line - Construct the Bostwick - East Walton 230kV line - Construct the East Walton - Jack's Creek 230kV line - At Bethabara, terminate the East Walton 230kV line - Loop the East Social Circle - East Watkinsville 230kV li…
TEAMS 09662 · plan p.130 · zone 212
GTC In the plan
p.10
Jun 1, 2027 No change Bethabara, Bostwick, Doyle, East Social Circle, East Walton, East Watkinsville, Jack's Creek, LG&E Monroe, Rockville, Scherer, Warthen
CC - TOMOCHICHI 500/230kV SOLUTION (NETWORK IMPROVEMENTS)
Build the new Tomochichi 500/230kV station splitting the Ohara - Scherer 500kV line. Build two 230kV lines from the new Tomochichi substation to the new Towaliga River 230kV substation with bundled 200C 1351 ACSS Martin. One will be 6 miles, and one will be 5 miles. Also adjust the tap settings on the 500/230kV transformer to address high voltage concerns on the 230kV system.
TEAMS 20717 · plan p.149 · zone 208
GPC In the plan
p.12
Sep 15, 2027 Delayed within 2027 Ohara, Scherer, Tomochichi, Towaliga River
CC - PROJECT SPEEDWAY (NETWORK IMPROVEMENTS)
Construct a new 500/230kV substation and loop in the Ohara - Scherer 500kV line. Install two 500/230kV auto transformers and build two new 1-mile 230kV lines each to Speedway #1 and Speedway #2, utilizing 200C 1351 ACSS Martin.
TEAMS 21332 · plan p.122 · zone 208
GPC In the plan
p.10
Jun 1, 2027 New project Hills Bridge, Ohara, Scherer, Speedway #1, Speedway #2
GTC: SMARR 500kV TRANSMISSION SERVICE
Construct the Rum Creek 500kV switching station. Loop in the existing Bonaire Primary - Scherer and O'Hara - Scherer 500kV lines. Terminate the new Big Smarr - Rum Creek 500kV line. Construct the new line using 100C (3) 1113 ACSR Bluejay conductor.
TEAMS 21345 · plan p.167 · zone 214
GTC In the plan
p.13
Jun 1, 2028 New project Big Smarr, Ohara, Rum Creek, Scherer
CC - DEER CREEK 500/230kV SOLUTION (NETWORK IMPROVEMENTS)
Build a 500/230kV station (Deer Creek) splitting the Bonaire Primary - Scherer 500kV line. Install two 500/230kV auto transformers and build 2 bundled 200C 1351 ACSS Martin 230kV lines from Deer Creek to Little Deer Creek.
TEAMS 21419 · plan p.156 · zone 214
GPC In the plan
p.12
Jun 1, 2028 New project Bonaire Primary, Deer Creek, Scherer

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.