Scherer
Named in 5 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
5projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| GTC: EAST WALTON 500/230kV PROJECT GTC: - Construct the East Walton 500/230kV substation - Construct the Bostwick 230kV switching station - Construct the East Walton - Rockville 500kV line - Construct the Bethabara - East Walton 230kV line - Construct the Bostwick - East Walton 230kV line - Construct the East Walton - Jack's Creek 230kV line - At Bethabara, terminate the East Walton 230kV line - Loop the East Social Circle - East Watkinsville 230kV li… TEAMS 09662 · plan p.130 · zone 212 |
GTC | In the plan p.10 |
Jun 1, 2027 | No change | Bethabara, Bostwick, Doyle, East Social Circle, East Walton, East Watkinsville, Jack's Creek, LG&E Monroe, Rockville, Scherer, Warthen |
| CC - TOMOCHICHI 500/230kV SOLUTION (NETWORK IMPROVEMENTS) Build the new Tomochichi 500/230kV station splitting the Ohara - Scherer 500kV line. Build two 230kV lines from the new Tomochichi substation to the new Towaliga River 230kV substation with bundled 200C 1351 ACSS Martin. One will be 6 miles, and one will be 5 miles. Also adjust the tap settings on the 500/230kV transformer to address high voltage concerns on the 230kV system. TEAMS 20717 · plan p.149 · zone 208 |
GPC | In the plan p.12 |
Sep 15, 2027 | Delayed within 2027 | Ohara, Scherer, Tomochichi, Towaliga River |
| CC - PROJECT SPEEDWAY (NETWORK IMPROVEMENTS) Construct a new 500/230kV substation and loop in the Ohara - Scherer 500kV line. Install two 500/230kV auto transformers and build two new 1-mile 230kV lines each to Speedway #1 and Speedway #2, utilizing 200C 1351 ACSS Martin. TEAMS 21332 · plan p.122 · zone 208 |
GPC | In the plan p.10 |
Jun 1, 2027 | New project | Hills Bridge, Ohara, Scherer, Speedway #1, Speedway #2 |
| GTC: SMARR 500kV TRANSMISSION SERVICE Construct the Rum Creek 500kV switching station. Loop in the existing Bonaire Primary - Scherer and O'Hara - Scherer 500kV lines. Terminate the new Big Smarr - Rum Creek 500kV line. Construct the new line using 100C (3) 1113 ACSR Bluejay conductor. TEAMS 21345 · plan p.167 · zone 214 |
GTC | In the plan p.13 |
Jun 1, 2028 | New project | Big Smarr, Ohara, Rum Creek, Scherer |
| CC - DEER CREEK 500/230kV SOLUTION (NETWORK IMPROVEMENTS) Build a 500/230kV station (Deer Creek) splitting the Bonaire Primary - Scherer 500kV line. Install two 500/230kV auto transformers and build 2 bundled 200C 1351 ACSS Martin 230kV lines from Deer Creek to Little Deer Creek. TEAMS 21419 · plan p.156 · zone 214 |
GPC | In the plan p.12 |
Jun 1, 2028 | New project | Bonaire Primary, Deer Creek, Scherer |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.
Site Scanner