Tomochichi

Named in 4 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
500, 230kV in the quote
GPC, GTCproject sponsor
4projects in the plan

Described as new. The quoted wording calls this substation new. “new Tomochichi 500/230kV station” — TEAMS 20717, plan p.149

Note. Georgia Power's project page says the project serves a large-load customer. It names two counties, so no county is given here. “The Tomochichi – Towaliga River Project includes the construction of new transmission lines and a substation in Butts and Spalding counties to support the electric needs of a large‑load customer that requires new transmission infrastructure.” — project page, retrieved 2026-11-20

The plan prints no county for this substation, and no utility project page found names one for it.

Location

33.2728, -84.1408 · Spalding County, GA · view on a map

Point published by the utility. The utility publishes this point, on a project map or in a filing. Accurate to about ±300 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: Printed by the sponsor: Georgia Power's Tomochichi – Towaliga River project page embeds its project map's configuration, with a location titled "Tomochichi Substation" at lat 33.27283687, lng -84.14076122; the printed path of proposed line 1 starts at exactly that position. Web-map marker, not a survey point: the page says "MAP NOT BASED ON FIELD SURVEY DATA" and "Structure and Line Locations based on Pre-Engineering data and subject to change". Accuracy ±300 m is a station-footprint allowance around a marker, not a survey figure.

County: the Census county at this point.

Sources: 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.149 · Georgia Power, Tomochichi – Towaliga River Project page (n/a (retrieved 2026-11-20)), About the Project; Project Map. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
CC - TOMOCHICHI 500/230kV SOLUTION (NETWORK IMPROVEMENTS)
Build the new Tomochichi 500/230kV station splitting the Ohara - Scherer 500kV line. Build two 230kV lines from the new Tomochichi substation to the new Towaliga River 230kV substation with bundled 200C 1351 ACSS Martin. One will be 6 miles, and one will be 5 miles. Also adjust the tap settings on the 500/230kV transformer to address high voltage concerns on the 230kV system.
TEAMS 20717 · plan p.149 · zone 208
GPC In the plan
p.12
Sep 15, 2027 Delayed within 2027 Ohara, Scherer, Tomochichi, Towaliga River
GTC: RUM CREEK - TOMOCHICHI (BLACK) 500kV LINE
Construct a second 500kV line from Rum Creek to Tomochichi (Black) which is approximately 30 miles long with 100C (3) 1113 ACSR Bluejay conductor. Make the necessary modifications at Rum Creek and Tomochichi to add breakers and terminate the line.
TEAMS 21073 · plan p.227 · zone 214
GTC In the plan
p.17
Dec 1, 2029 Advanced from 2030 to 2029 Rum Creek, Tomochichi
BIG SOUTH GRIFFIN - TOMOCHICHI 230kV NEW LINE
Build a 7 miles 230kV line from Tomochichi to South Griffin using 200C 1351 ACSS Martin conductor.
TEAMS 21580 · plan p.154 · zone 208
GPC In the plan
p.12
Jun 1, 2028 New project Big South Griffin, Tomochichi
MCDONOUGH - TOMOCHICHI 230kV NEW LINE
Build a 13 miles 230kV line from Tomochichi to McDonough using 200C 1351 ACSS Martin conductor. Install a 230/115kV auto transformer at McDonough.
TEAMS 21581 · plan p.174 · zone 208
GPC In the plan
p.13
Jun 1, 2028 New project MCDONOUGH, Tomochichi

Generation interconnection requests filed in Spalding, GA: Southern Company queue, 2 active of 3. Same county, not the same substation.

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.